Rest between shifts in the UK: 11 hours on three shifts
In the UK and Ireland, a worker is entitled to 11 consecutive hours of rest between working days. On a plant running earlies, lates and nights, most rota days clear that easily: a normal day off between shifts is 16 hours. The breaches come at a small number of changeovers, and every one of them leaves exactly 8 hours. If you know which three moves cause them, you can check a four-week rota in a few minutes.
This post covers what the rule says, the shift-change exemption that people often lean on too hard, the three changeovers to look for, and the one place a rota checked on its own still misses: the join between this rota and the last one. At the end there is a table you can copy.

What the rule says
In Great Britain, regulation 10 of the Working Time Regulations 1998 says: "A worker is entitled to a rest period of not less than eleven consecutive hours in each 24-hour period." Young workers get 12. GOV.UK puts it simply: "if they finish work at 8pm, they should not start work again until 7am the next day."
Ireland's rule is the same number. Section 11 of the Organisation of Working Time Act 1997 gives an employee "a rest period of not less than 11 consecutive hours in each period of 24 hours during which he or she works for his or her employer".
Eleven hours is the gap from the end of one shift to the start of the next. Travel, handover and changing time do not shrink the rule, but they do shrink what the person actually gets, which is why most sites aim above it.
The shift-change exemption, and what it costs
Both countries let the rule give way when someone changes shift. In Great Britain, regulation 22 says the daily rest rule "does not apply in relation to a shift worker when he changes shift and cannot take a daily rest period between the end of one shift and the start of the next one". In Ireland, the Workplace Relations Commission's Code of Practice on Compensatory Rest Periods lists the same case: "shift workers who change shift and cannot avail themselves of the rest period". Separately, Ireland's General Exemptions Regulations cover "any industrial activity in which work cannot, by reason of considerations of a technical nature, be interrupted".
Neither is free. The UK's regulation 24 says the employer "shall wherever possible allow him to take an equivalent period of compensatory rest". Ireland's regulations say the employer "shall ensure" a rest that "can reasonably be regarded as equivalent", and the Code says it should come "as soon as possible and, generally, in an adjacent time frame".
So a short changeover is not a free pass. It is three hours of rest you owe the person, and someone has to give it and be able to show it was given. The UK wording also covers a worker who "cannot take" the rest. A rota that could have given 11 hours and didn't is a weak place to rely on it. Whether the exemption fits your site is a question for your adviser. The rest of this post assumes the simpler goal: a rota with no short changeovers in it.
The three changeovers that leave 8 hours
Take a common 8-hour pattern: earlies 6am–2pm, lates 2pm–10pm, nights 10pm–6am. Here is every move from one shift to the next working shift, and the rest it leaves.
| From | To | Rest | Clears 11 hours? |
|---|---|---|---|
| Early | Early, next day | 16 hours | Yes |
| Late | Late, next day | 16 hours | Yes |
| Night | Night, next night | 16 hours | Yes |
| Early | Late, next day | 24 hours | Yes |
| Late | Night, next day | 24 hours | Yes |
| Night (ends 6am) | Early, the following day | 24 hours | Yes |
| Late | Early, next day | 8 hours | No |
| Night (ends 6am) | Late, same day | 8 hours | No |
| Early | Night, same day | 8 hours | No |
The pattern is plain once it is laid out. Moving forward through the day (early, then late, then night) gives 24 hours at the change. Moving backward, or doubling back on the same day, gives 8. The late-into-early "quick return" is the one that turns up most, usually from a swap or a cover request rather than from the pattern itself.
The join between two rotas
Most short changeovers that get through are at the boundary. A four-week rota is built and checked on its own, and every changeover inside it is fine. But the person who worked the last late on the Sunday of the old rota starts the new one on a Monday early. That is 10pm to 6am: 8 hours. Neither rota shows it, because each one only contains half of the pair.
The fix is one extra line in the check: for every person, compare the last shift of the old rota with the first shift of the new one. If your rota tool does not look back across the join, do this one by hand.
A check you can copy
Run this on the draft rota before it goes out. It takes a few minutes for a team of 40.
| Step | What to do | Your rota |
|---|---|---|
| 1 | Write your shift times. Early, late, night (and any 12-hour or split shifts) | |
| 2 | For each pair of shifts, work out the gap from the end of one to the start of the next. Mark any under 11 hours | |
| 3 | Search the draft for every marked pair, person by person | |
| 4 | For each person, compare the last shift of the old rota with the first of the new | |
| 5 | Check every swap and cover change made after the rota went out against the same marked pairs | |
| 6 | If you rely on the shift-change exemption for one: write down when the compensatory rest will be given |
Step 2 is a one-off. Once you have the marked pairs for your shift times, steps 3 to 5 are a search. If you would rather paste a week of shifts and have the short gaps named, the free rest break checker does that, with no sign-up.
Where this stops
Fivexer's UK and Ireland rules check the 11 hours between every pair of shifts for each person, including the last shifts of the rota before. A draft that breaks it names the person and the shift, and publishing stops until you change it or choose to publish anyway. It does not apply the shift-change exemption, so a changeover you have decided to treat that way shows as a breach. It also does not keep a record of compensatory rest owed or given. That stays in your own records.
For the rest of the rules that shape a three-shift plant, such as night work limits and weekly rest, the rest break checker covers twelve countries and the EU floor.
Next step: take your next rota, list each person's last shift of the old one beside their first of the new, and look for a late followed by an early.